TRC Rehearsal Room 2: labor plan v1.0 (2026-09-26)

Every hour here is the same hour in costs.csv (rows LB-01 to LB-29) and summary.json. Total: 424 hours, $43,250 at the expected rates, 29 tasks, 11 trades. Regenerate with python3 spec/tools/build_costs.py && python3 spec/tools/build_labor_md.py.

Both ways at a glance

GC crew Greg + one handyman on weekends
Hours on site 424 billed hours 320.5 crew person-hours + 140 licensed-pro hours
Labor cost, expected $43,250 + $11,002 GC fee $17,420 pros + $14,422 handyman
Calendar on site 30 days (22 working days) 80 days (12 weekends)
First order to finished room 66 days (2026-09-28 to 2026-12-03) 85 days (2026-09-28 to 2026-12-21)
Project total, expected $156,970 $131,200

Rates used (Los Angeles, billed to the client, 2026)

Billed rates carry the contractor's insurance, truck, tools, overhead and profit, so they run 2 to 3.5 times the wage. Wages are the BLS OEWS May 2025 mean hourly wage for the Los Angeles-Long Beach-Anaheim metro (series OEUM0031080000000xxxxxx03, read through the BLS public API on 2026-09-26).

Trade Low / pick / high $/hr LA mean wage (BLS) Pick / wage Hours Cost at pick
electrician 100 / 135 / 160 $39.57 (47-2111 Electricians) 3.4x 103 $13,905
gc carpenter 75 / 110 / 150 $37.79 (47-2031 Carpenters) 2.9x 46 $5,060
handyman 60 / 90 / 120 $28.07 (49-9071 Maintenance and repair) 3.2x 51 $4,590
glazier 70 / 95 / 150 $36.17 (47-2121 Glaziers) 2.6x 37 $3,515
plaster 70 / 95 / 130 $30.58 (47-2161 Plasterers) 3.1x 36 $3,420
finish carpenter 70 / 95 / 130 $37.79 (47-2031 Carpenters) 2.5x 36 $3,420
av 75 / 100 / 135 $29.76 (49-2097 AV equipment installers) 3.4x 28 $2,800
flooring 45 / 70 / 95 $33.48 (47-2042 Floor layers) 2.1x 31 $2,170
drywall 60 / 85 / 120 $34.64 (47-2081 Drywall installers) 2.5x 25 $2,125
painter 55 / 75 / 100 $29.71 (47-2141 Painters) 2.5x 15 $1,125
assembler 50 / 70 / 90 $30.39 (47-2061 Construction laborers) 2.3x 16 $1,120
Total 424 $43,250

Billed-rate evidence: - Electrician. Angi's Los Angeles guide (March 2026) gives $58-115/hr for residential service work; HomeGuide's 2026 national range is $50-130. The $135 pick sits above both because this is a permitted commercial job for a C-10 shop, including Lutron RadioRA 3 programming. The $100 low end is the fair bid from a small shop. Confidence: moderate. https://www.angi.com/articles/how-much-does-it-cost-hire-electrician/ca/los-angeles , https://homeguide.com/costs/electrician-cost-per-hour - Handyman. LA scheduled work runs $68-115/hr with a $90 average (localservicecost.com, built from the BLS wage times 1.5-2.5); licensed handymen in West LA run $75-150 (GoldKey Repairs). The $90 pick matches the average. https://localservicecost.com/services/handyman/california/los-angeles/ - Plaster. One LA Venetian plaster installer quotes $14-16/sq ft installed. This spec carries $3,420 of labor plus about $753 of Roman Clay on ~400 sq ft, or $10.40/sq ft, with the skim coat priced separately under drywall. Together they land at $16.20/sq ft, at the top of that quote. https://venetianplasterlosangeles.com/ - Other trades are set at 2.1 to 3.4 times the BLS wage, the same markup range the handyman and electrician evidence implies. Confidence: moderate. None of these rates is a quote; three bids replace them.

Task by task (GC crew)

Day numbers are working days on the GC schedule below. The DIY column shows who does the task on the weekend path and the person-hours after the slowdown factor (amateur plaster and skim take 1.5 times as long, carpentry 1.4 times).

ID Phase Task Trade Hours Crew Day(s) Cost DIY: who DIY person-hours
LB-01 demo Move gear and furniture out, protect floor and booth, dust barrier handyman 8 2 1 $720 Greg + handyman 8
LB-02 demo Strip stretched fabric, fabric track, chair rail; pull staples handyman 12 2 1-2 $1,080 Greg + handyman 14.4
LB-03 demo Lift the floating oak LVP (salvage) flooring 10 1 2 $700 Greg + handyman 12
LB-04 demo Haul-away and site clean after demo handyman 3 2 2 $270 Greg + handyman 3
LB-05 framing Blocking: mirror-wall cleat line, ceiling-inset frame through the troffer openings, guitar and shelf backing; patch cut-ins gc carpenter 16 2 3 $1,760 Greg + handyman 22.4
LB-06 drywall Patch troffer holes and track damage, Gardz seal, two skim coats ~540 sq ft, sand, prime drywall 25 2 7-10 $2,125 Greg + handyman 37.5
LB-07 electrical Four new 20A circuits incl. two isolated-ground (C1-C4), panel work electrician 20 2 3-6 $2,700 licensed pro (kept) 20
LB-08 electrical Remove 3 troffers (2 room + 1 booth); cut in and wire 8 DMF downlights (1.5 h each) electrician 14 2 3-6 $1,890 licensed pro (kept) 14
LB-09 electrical Track feed and 4 heads over the guitar wall electrician 3 2 4 rough, 17 heads $405 licensed pro (kept) 3
LB-10 electrical LED: 7 driver J-boxes, feeds, 80 ft cove channel, arch halo channels, ceiling brass channel, bar/shelf channels, solder and test ~211 ft of tape electrician 35 2 4-6 rough, 16-18 trim $4,725 licensed pro (kept) 35
LB-11 electrical RadioRA 3 processor, 7 dimmers, keypad, programming 4 scenes, flicker check on camera electrician 16 1 18 $2,160 licensed pro (kept) 16
LB-12 electrical 8 isolated-ground receptacles on C1/C4, relabel panel electrician 9 2 5 rough, 18 trim $1,215 licensed pro (kept) 9
LB-13 electrical Permit, rough and final inspections, Title 24 forms electrician 6 1 7 rough, 19 final $810 licensed pro (kept) 6
LB-14 paint Ceiling: patch-prime and one coat Tricorn Black painter 6 1 10 $450 Greg + handyman 7.8
LB-15 paint Doors D-2, D-3 and frames, both booth slider frames touch-up: black enamel painter 9 1 13 $675 Greg + handyman 11.7
LB-16 plaster Roman Clay: base coat, two troweled coats, burnish, topcoat on ~400 sq ft plaster 36 2 11-14 $3,420 Greg + handyman 54
LB-17 flooring Install ~300 sq ft NuCore, undercut jambs, two brass reducers flooring 21 2 15-16 $1,470 Greg + handyman 27.3
LB-18 millwork Set and anchor bar carcass, glass front on standoffs, brass edge; stone fabricator templates and sets the top (in their price) finish carpenter 8 2 16-17 $760 Greg + handyman 11.2
LB-19 millwork Two floating bottle shelves on Shelfology rods finish carpenter 4 1 17 $380 Greg + handyman 5.6
LB-20 millwork Fluted slat panels W-02/W-03, angled cuts, top fillers finish carpenter 8 2 16 $760 Greg + handyman 11.2
LB-21 millwork Route five MDF arch backers, mount French cleats finish carpenter 8 2 14, in the shop $760 Greg + handyman 11.2
LB-22 millwork 10 guitar hangers on a laser line; D-3 seal kit; 2 lever sets finish carpenter 8 1 17-18 $760 Greg + handyman 11.2
LB-23 mirror Mount five arch mirrors to backers, brass frames, halo channel alignment glazier 21 2 17-18 $1,995 licensed pro (kept) 21
LB-24 mirror Ceiling inset: 2 ply panels to blocking, 16 filmed tiles with clips, brass perimeter glazier 16 2 11 $1,520 licensed pro (kept) 16
LB-25 furniture Receive, unbox, assemble: sectional, 2 swivels, 3 stools, desk (bolted), rack, benches, rugs, plants, art assembler 16 2 19 $1,120 Greg + handyman 16
LB-26 acoustics Hang 12 booth panels, 6 main-room panels (2 as ceiling clouds), 4 corner traps handyman 12 2 19 $1,080 Greg + handyman 12
LB-27 av Re-rack, re-cable desk to rack to IB1/HS8/sub, label R-01.., patch map, display arm, Trinnov recalibration, REW before/after av 28 2 20-21 $2,800 Greg + handyman 28
LB-28 closeout Punch list, final clean, move gear back handyman 16 2 22 $1,440 Greg + handyman 16
LB-29 management GC project management and site supervision gc carpenter 30 1 all $3,300 dropped -
Total 424 $43,250 320.5 crew + 140 pro

Hours by the trade groups in the brief: demo 33, framing 16, drywall 25, electrical 103, paint 15, plaster 36, flooring 21, millwork 36, mirror 37, furniture 16, acoustics 12, av 28, closeout 16, management 30.

What is priced elsewhere and carries no line here: - Stone top. The fabricator's price (B-01F) includes fabrication, delivery and setting. Order it cut to the approved shop-drawing size (a 48 x 24 in rectangle with one eased edge), so it arrives with the carcass instead of 1-2 weeks after a site template. - Upholstery. Every seat is bought finished, so there is no upholstery labor. Only the pillow inserts need changing if Greg wants a firmer fill. - Booth refresh. The booth's two downlights are among the 8 in LB-08, its 10 ft of tape is in LB-10, and its 12 absorbers are in LB-26. - Piano delivery. K-01D covers the stair surcharge; the dealer's crew sets the piano.

Sequence and critical path (GC crew)

Twenty-two working days on site. With the dates in SCHEDULE.md that is Monday 2026-11-02 to Thursday 2026-12-03, 32 calendar days, because Thanksgiving takes two days out of the fourth week; without a holiday it is 30. The chain that sets the finish:

demo (days 1-2) → blocking (3) → electrical rough (3-6) → rough inspection (7) → patch and two skims with overnight dry (7-10) → ceiling paint (10) → Roman Clay with its drying time (11-14) → floor (15-16) → millwork and arch mirrors (16-18), electrical trim and scenes alongside (16-18) → final inspection (19) → furniture and acoustics (19) → AV (20-21) → closeout (22).

Day Work on site Crew on site
1 Move out, protect booth and corridor, ZipWall; strip fabric and track 2 handymen
2 Finish strip, lift the oak LVP and stack it for salvage, haul 2 handymen + floor installer
3 Blocking for the mirror cleat line, ceiling-inset frame, guitar and shelf backing. Electrician starts rough-in 2 carpenters, electrician + helper
4-6 Four circuits, 8 can cut-ins, track feed, 7 driver J-boxes and 120 V feeds, IG boxes electrician + helper
7 City rough inspection (book it when the permit is pulled); patch and Gardz right after sign-off inspector, 2 drywallers
8-10 Two skim coats with overnight dry, sand, prime; ceiling Tricorn Black on day 10 2 drywallers, painter
11 Plaster base coat. Ceiling-inset ply panels and 16 mirror tiles with clips and brass perimeter 2 plasterers, 2 glaziers
12-14 Two troweled Roman Clay coats, burnish, topcoat; doors and frames in black enamel on day 13. Arch backers routed in the carpenter's shop on day 14 2 plasterers, painter
15-16 NuCore floor, undercut jambs, brass reducers 2 installers
16-17 Bar carcass set and anchored, stone top set by the fabricator, bar glass, slat panels, shelves 2 finish carpenters, stone crew
16-18 Electrician lands tape, drivers, track heads and dimmers; RadioRA 3 programming and camera flicker check on day 18 electrician + helper
17-18 Five arch mirrors with brass frames and halo channel; guitar hangers, door seal and levers 2 glaziers, 1 carpenter
19 City final inspection; furniture received and assembled; panels and traps hung; piano delivered inspector, 2 assemblers, 2 handymen
20-21 Re-rack and re-cable, label R-01.., Trinnov recalibration, REW after-sweep AV tech + helper
22 Punch list, final clean, gear back 2 handymen

Float: the door enamel (day 13) and the bottle shelves can slip two days without moving the finish. Nothing on the chain above can slip without moving it.

Greg + one handyman on weekends

Greg and one handyman work Saturdays and Sundays, 8 hours each, 32 person-hours a weekend. The licensed electrician (103 h) and glazier (37 h) work the weekdays in between, and inspections happen on weekdays. There is no GC management time on this path. The 320.5 crew person-hours fill about ten weekends; the drying time for skim and plaster and the inspection gaps stretch that to twelve.

Weekend Crew work (person-hours) Weekdays after it
1 Move out, protect, strip fabric and track, lift LVP, haul (37) Electrician starts rough-in
2 Blocking for mirror, ceiling inset, guitars, shelves (22) Electrician finishes rough-in; rough inspection
3 Patch, Gardz, skim coat 1 (19)
4 Skim coat 2, sand, prime; ceiling Tricorn Black (26)
5 Roman Clay base coat and first troweled coat (18)
6 Second troweled coat; doors and frames in enamel (30)
7 Burnish and topcoat (18) Glazier sets the ceiling inset
8 NuCore floor and reducers (27)
9 Arch backers and cleats, bar carcass, slat panels (34) Stone top set; glazier sets the five arches
10 Shelves, guitar hangers, door seal and levers, bar glass (17) Electrician trims out and programs; final inspection
11 Furniture assembly, panels and traps (28)
12 Re-rack, re-cable, label, calibrate, punch, clean (44; runs into Monday evening)

The weekend crew is the slow part: the paid handyman bills for half of every crew hour ($14,422 expected) and Greg supplies the other half unpaid. A handyman paid for more than $1,000 of work on a permitted job needs a CSLB license (B&P 7048 as amended by AB 2622, 2025), or must be TRC's W-2 employee with workers' comp.

What the hours assume